ZANAGA PROJECT UPDATE
Zanaga Iron Ore Company Limited (“ZIOC” or the “Company”) (AIM: ZIOC) is pleased to provide an update to shareholders on work being conducted on the Zanaga Iron Ore Project (“Zanaga” or the “Project”).
Highlights
· Iron ore market
o Premiums for high quality iron ore pellet feed concentrates, and pellets, are at record highs
o These premiums are indicative of a structural shift in the pricing of iron ore products to appropriately value the benefit of higher quality ores to customers
o The Zanaga Project is well positioned due to the capability of beneficiating its iron ore into high iron content products with low impurities
o ZIOC continues to believe in the long term economic benefit of producing high quality iron ore products and continues to plan for premium quality iron ore production from all phases of the Project’s development
· Early Production Project
o Progress made in assessing the opportunity for a small scale Early Production Project (“EPP”)
o Preliminary test work results indicate that a small scale project is capable of producing a premium product pellet feed concentrate with an iron ore grade of 66.6% with low impurities
o Test work is ongoing as regards the feasibility of pelletising this concentrate using a polymer based process into a pellet product of sufficient quality to meet industry standards and be commercially marketable
o Logistics routes to two potential exit ports are under review
§ Road only, and combination road plus rail routes within Republic of Congo (“RoC”) to the port of Pointe-Noire
§ Road and rail through Gabon to the port of Owando (Libreville)
o Glencore and ZIOC have agreed to conduct further study work on the EPP project, including assessment of EPP project feasibility, scope of operations and project economics
o Further updates on the EPP study work program are expected to be announced in Q2 2018
· 30Mtpa staged development project (12Mtpa Stage One, with 18Mtpa Stage Two expansion)
o Review of the 12Mtpa Stage One development project as outlined in the 2014 Feasibility Study
§ High level analysis of capital and operating cost estimates (“FS review”) completed in May 2017 to assess potential savings achievable
§ FS review indicated significant savings achievable across both capital and operating cost estimates for the 12Mtpa Stage One development project, including:
· Capital expenditure savings potential of 8-9% (U$153-371m), reducing the 12Mtpa Stage One capital cost estimate to between U$1,797-U$2,041m
· Operating expenditure savings potential of 15-20%, reducing the 12Mtpa Stage One operating cost estimate to between U$23-24 per dry metric tonne
§ Project Team continue to evaluate the 30Mtpa staged development project. However, assessing the EPP project is a near-term priority due to the benefits of reduced upfront capital cost, and ability to derisk the larger project
o Environmental Permit
§ As announced in November 2017, Environmental Permit awarded in November 2017, covering the Stage One 12Mtpa development phase of the Zanaga Iron Ore Project as outlined in the Project’s Mining Licence
o Port agreements
§ ZIOC notes that there is still discussion between the RoC Government, China EXIM Bank and China Road and Bridge Corporation (CRBC) on the financing and development plan for the new bulk materials port development north of Pointe Noire
§ Advancement of the new port development could provide a key catalyst in allowing the Zanaga 12Mtpa Stage One development project to derisk and proceed towards seeking finance
o Power agreements
§ The Zanaga Project team continue to investigate power solutions with independent power providers and equipment suppliers with an aim to seek an optimal solution to the energy requirements of the 12Mtpa Stage One mining project
· Ore sample consolidation program
o Zanaga Project ore samples consolidated into two sites in order to allow efficient response to requirements of the various test work programs
· Funding Agreement signed with Glencore for 2018 work program
o US$1.53m budget approved for 2018, which amount is funded 50% by Glencore and 50% by ZIOC
o Budget allows for funding study work on the EPP project including specific product test work on the pellet feed and pelletisation products and scoping of the EPP project’s viability and economics
o US$3.8m cash on hand at ZIOC as at 28 February 2018
Clifford Elphick, Non-Executive Chairman of ZIOC, commented:
“We are pleased to announce the results of the work that has been done over the past few months. Both Glencore and ZIOC teams involved in the project have worked very well together in assessing the new options available to develop the Zanaga Project.
The early production project (“EPP”) is targeting a low capital cost operation utilising existing road and potentially rail transportation solutions as well as existing port infrastructure. If we are successful in developing this low capital cost solution, we expect the Project would be attractive for third party financing. Furthermore, this strategy is aligned with a desire to implement the Project’s initial production phase and derisk the operation in advance of preparing for financing of the larger 12Mtpa Stage One project.
The Project Team have also conducted initial studies both internally and with third parties to assess the potential capital and operating costs savings that could be achieved for the 12Mpta initial phase of the staged development project, as outlined in the Feasibility Study completed in 2014. The initial review of these figures has indicated potential for major capital and operating cost savings that encourages us to continue to pursue pathways available for development of this much larger development phase, simultaneously with the EPP option currently under review.
It is important to highlight to our investors the extent to which dynamics in global iron ore markets have seen positive change over the past two years, and the last few months in particular. We continue to see better than expected iron ore demand fundamentals and have been particularly pleased to see pricing for higher quality products achieving record premiums. This is substantially driven by China’s determination to reduce pollution levels, improve efficiency in transforming iron ore into steel, and supports the need for more iron ore production from assets like Zanaga with high iron content characteristics and particularly low impurity levels.
The Zanaga Project Team continues to investigate logistics and product options for the EPP project as well as its scope of operations and project economics and we intend to provide more details about this workstream during Q2 2018.“