LERALA DIAMOND MINE COMMISSIONING UPDATE
Highlights from the announcement include:
Last phase plant commissioning nearing completion
Diamond concentrate build up in the Plant, with diamond recovery to commence
First diamond sale scheduled in August
Now ramping to full production and Name Plate handover
DiamonEx Limited (AIM:DON), the emerging diamond producer in Botswana, announces that following on from its commissioning update in May 2008, the last phase of commissioning at its Lerala Diamond Mine Processing Plant (‘Plant’) will complete this week leading to the commencement of diamond recovery. Last phase commissioning, referred to as ‘hot commissioning’ involves
1.The processing of ore through the entire Plant – complete;
2.The batch feeding of ore into the Plant – currently being undertaken;
3.The continuous feed of ore into the Plant and with that the recovery of diamonds – once batch feeding completed.
Managing Director of DiamonEx, Dan O’Neill said, ‘The commissioning process has gone well with no major issues emerging. It has overrun by around three weeks due to some technical issues in Plant operation but on the whole the Plant has tested well. The Lerala Mine team under the leadership of Mark Coetzee, our General Manager at Lerala, and our Project Manager, Promet Engineering from Cape Town, must be congratulated on their effort in building and commissioning this state of the art Plant. We are all very proud of what we have achieved and created, and look forward to the next challenge of optimising diamond recovery and generating cash flow.