Gippsland Limited (GIP) – Abu Dabbab Project Update
Gippsland Limited who have the 40 million tonne Abu Dabbab tantalum-tin project which is expected to become a major supplier to the global tantalum industry are relocating their plant site:
Highlights
• Plantsite to relocate to within 1km of the open pit mine
• Relocation and use of seawater provides significant financial benefits – operating cost savings of approximately US$18 million over the Abu Dabbab mine life
As a result of the recent decision to utilise seawater for the process plant, re-injection of waste brine becomes unnecessary which in turn enables the plantsite to be relocated within 1km of the open pit mine. This change will reduce the 2 million mill feed haulage distance by some 18km, thereby eliminating the need for a heavy haulage mill feed fleet whilst reducing haulage costs by approximately US$4 million per year. The access road between the mine and the coast will now become a light vehicle route that does not need to cater for use by the project’s heavy duty mill feed haulage vehicles. The use of seawater will result in a capital saving of approximately US$4 million and an operating cost savings of approximately US$900,000 per year or US$18 million over the likely Abu Dabbab mine life.
The new plant site will also shorten the mill feed distance from the Company’s 98Mt Nuweibi tantalum deposit located some 16km to the south of the Abu Dabbab plantsite. However as Abu Dabbab will have a mine life of approximately 20 years, Nuweibi will not be utilised for at lease a decade. The relocation of the plantsite will not adversely affect the timing of the commencement of production in 2011.
Jack Telford, Executive Chairman of Gippsland Ltd commented,