Coal of Africa Project Progress
Project Highlights
- Vele coking coal resource upgrade from 441 mt to 721 mt;
- Makhado coking coal project to produce 5 mtpa at a mining cost of US$43 per saleable tonne;
- Vele coking coal project to produce 5 mtpa at a mining cost of US$54 per saleable tonne;
- Mooiplaats FOB cost Richards Bay US$ 37 per saleable tonne;
- Port capacity secured at both Richards Bay and Maputo;
- Mooiplaats thermal coal project on track for mining commencement in Q4 2008;
- Current cash resources of A$240 million, no debt.
Coal of Africa Limited, the coal development company operating in South Africa, is pleased to announce that significant progress continues to be made toward the development of the Company’s coal projects in South Africa.
Makhado Coking Coal Project – Soutpansberg Coalfield
The latest coal resource update for the Makhado Project, announced on 22 July 2008, has increased resources to in excess of 1.3 billion tonnes, of which over 230 million tonnes are in the “measured” category.
Vele Coking Coal Project– Tuli Coalfield
A New Order Mining Right Application is scheduled for submission by the end of September 2008. A 65-hole geological drilling program has been completed and three bulk sample sites consisting of 31 large diameter cored boreholes have been completed, logged and submitted for preliminary analysis. Initial results indicate a significant improvement of coking coal qualities and yield when compared to historical results, indicating the primary resource is a classic hard coking coal rather than the expected semi-soft. Testing indicates a washed product with phosphorous levels below .01%.
Mooiplaats Thermal Coal Project – Ermelo Coalfield
The first JOY continuous miner is ready for handover, and the contract with the mining contractor is anticipated to be finalised this month.
Initial coal mining by continuous miner is now planned to commence in November 2008, following the establishment of access portals, ventilation fans, incline conveyor and temporary stockpiles.
Surface infrastructure is being established, and plant design has been finalised. The first plant modules are scheduled for commissioning in February 2009.