10
Dec
Coal of Africa Ltd (CZA) – Project updates
Comments
Updates
• Rail allocation secured with Transnet Freight Rail (“TFR”) for the Mooiplaats Thermal Coal Project to meet Company’s 3 million tonne port allocation at Richards Bay
• Current cash of A$ 225 million, no debt
• First coal cut at Mooiplaats and development of underground access portals progressing according to schedule
• Vele Project mining plan revised to include both opencast and underground mining, generating better yields, lower operating costs and an extended mine life
• Independent Power Producer (“IPP”) submissions relating to both the Vele and Makhado Projects shortlisted by Eskom
• Reviewing the potential of a Main Board listing on the London Stock Exchange